Chuchawal Royal Haskoning is the PM/CM for this Project in Wang Noi, Ayuthaya. The DC will be constructed in six months from January 2006 till June 2006 for fast construction, the design uses pre-cast columns and beams.
The building of 22,000 sq.m. will have 15,500 sq.m. for stocking, 5,400 sq.m. for flow thru.